Completed tower top enclosures on the towers of the 1915 Çanakkale Bridge, aerial view
Bridge References

Bridge Projects

Rehabilitation, erection and specialist works on Türkiye's landmark bridges, from the Golden Horn to the Dardanelles. Each bridge page shows what we did on that structure.

By type of work

What we have done on bridges in service

Damper Installation

On the Bosphorus Bridge we installed four viscous dampers between the towers and the deck. The hangers had been changed from inclined to vertical, and the deck needed dampers at the towers. We installed them from a platform hung from the footwalk, under the same contract as the tower strengthening.

Expansion Joint Replacement

We remove old expansion joints and install new modular joints supplied by their manufacturer. On the Bosphorus Bridge we replaced the joints at both ends in four phases, with the bridge open to traffic.

Orthotropic Deck Crack Repair

We repair fatigue cracks in orthotropic steel decks, each crack to the repair detail for its type. On the Fatih Sultan Mehmet Bridge we repaired 1,576 cracks of 21 types from inside the deck, with the bridge open to traffic. On the Bosphorus Bridge we repaired 611 cracks under the tower strengthening contract and a further 59, of eight types, in 2020.

Strengthening & Steel Replacement

We strengthen existing bridge steel and replace the parts that have to be renewed. In the four tower legs of the Bosphorus Bridge we erected 412 tonnes of stiffeners and diaphragms between +4.50 m and +149.25 m. At the four tower-deck junctions of the same bridge we removed the plates and girders of the widened walkway sections around the towers and erected new steel fabricated to the measured dimensions of the old. On the Fatih Sultan Mehmet Bridge we welded additional gusset plates to the existing hanger plates on site.

By type of work

What we have done on new bridges

Expansion Joint Installation

On new bridges we install the modular expansion joints supplied by their manufacturer. On the 1915 Çanakkale Bridge we lowered four 55-tonne joints into place with a 350-tonne mobile crane, preset each opening to the temperature at the time of installation and welded the joints in on site.

Access Structures

We deliver permanent steel access structures as one package, from shop drawings and design calculations to galvanising and erection. On the 1915 Çanakkale Bridge we delivered around 112 tonnes of galvanised stairs, cage ladders, platforms, handrails and gratings for the anchor chambers on both sides of the strait, 15 viaduct piers and the side-span piers.

Tower Top Erection

We erect steelwork at the top of bridge towers. On the 1915 Çanakkale Bridge we erected the four steel artillery shell figures on the legs of the two 318 m towers: pieces of up to 13.5 tonnes, lifted by tower crane to +313.5 m and joined with site welds and bolts.

Temporary Works

We assemble and dismantle the temporary steelwork a bridge needs while it is being built. On the 1915 Çanakkale Bridge we provided the bolted-connection crew for the shipyard assembly of the temporary working platform between the two towers in 2019, and in 2023 we dismantled around 1,400 tonnes of temporary steelwork from both towers and both anchor blocks.

FAQ

Frequently asked questions

Do you work while the bridge is open to traffic?

Yes. On the Bosphorus Bridge we replaced the expansion joints in four phases with the bridge open, each phase closing two lanes. On the Fatih Sultan Mehmet Bridge, each opening we cut in a rib was cut and plated within a single overnight closure of the lane above.

Do you supply the expansion joints?

No. The manufacturer supplies the joints; we remove the old ones and install the new. On the 1915 Çanakkale Bridge the four joints arrived complete from their manufacturer, and our contract covered the site work from loading at the laydown area to welding, bolt tightening and corrosion protection of the weld areas. On the Bosphorus Bridge we supplied the strengthening steel at the joint zones.

Who prepares the method statements?

We do. On the Fatih Sultan Mehmet Bridge we wrote a separate method statement for each of the 21 crack types, based on its approved repair detail. For the 2020 repairs on the Bosphorus Bridge we prepared method statements for five of the eight crack types.

Who inspects the welds?

Third-party inspection firms. On the 1915 Çanakkale Bridge expansion joints an NDT contractor carried out VT, MT and UT for us, and each joint has a fit-up report, weld log, NDT reports and a bolt-tightening report. On the crack repairs, non-destructive testing took place no earlier than 24 hours after welding.