Bosphorus Bridge Tower-Deck Junction Repair
Nunteknik removed the plates and girders of the widened walkway sections around the towers at the four tower-deck junctions of the 15 July Martyrs Bridge (Bosphorus Bridge) in Istanbul and erected new steel fabricated to the measured dimensions of the old.
Plates and girders replaced at four tower-deck junctions
On the Bosphorus Bridge, the walkway widens around each tower where the tower meets the deck. These four widened walkway sections, on the north and south sides of the Ortaköy and Beylerbeyi towers, were to receive new plates and girders. As the subcontractor, we prepared the method statement, set up the access platform and winches, removed the old steel, and took on fabrication, erection, welding and painting of the new steel. Our scope also covered 73 repairs under the main deck.
Access beneath the junction, matching existing steel
Reaching the old members meant working beneath the widened walkway section at elevation +58.00, from a platform assembled at the tower leg and pulled up by winch ropes passed through openings in the walkway. The new plates and girders would connect to the existing steel of the bridge, so their dimensions had to come from the removed piece itself. The work ran at four locations, two on each side of the Bosphorus, with the platform re-rigged at each, and dismantling and erection took place in night lane closures.
A platform slung from the girders, steel made to measure
We assembled the platform from four pieces at the tower leg and lowered the winch ropes through openings in the walkway. We then raised the platform to +58.00 and hung it on wire-rope slings from lugs welded under the girders. After removing the hinged plates, we took out the main plate with its girders in one piece by mobile crane and sent it to our partner shop. The replacement was fabricated to its dimensions, blast-cleaned and painted. All welding on the main connection was done in the shop. We set the new piece in place whole, made the main connection with bolts, and completed the secondary site welds and touch-up painting.
New steel at four junctions, final acceptance
All four widened walkway sections now have new plates and girders, and the 73 repairs under the main deck were completed. An independent inspection body checked the welds by magnetic particle testing; the five reports covering the four locations record them as accepted, some after repair. Provisional acceptance with the main contractor was granted in March 2020 and final acceptance in March 2021. Both certificates record nothing standing in the way of acceptance.
What this project actually required
Not a generic service list — the specific capabilities exercised on this package.
The stages we delivered on this project
Select a stage to see how it was carried out and controlled.
Engineering
Engineering and method statements, approved before work starts.
Fabrication
Steel fabricated in EN 1090 certified partner shops under our quality control, to approved welding procedures (WPS).
Erection
Steel erected by our own crews and, where the work calls for it, by subcontractors we manage.
Testing
Non-destructive testing of critical welds.
From the fabrication shop to the completed structure
More from the bridge & infrastructure record

1915 Çanakkale Bridge Anchor Block and Pier Access Structures

Galata Bridge Bascule Leaf Repair

Bosphorus Bridge Tower Strengthening and Damper Installation
Planning comparable bridge or infrastructure work?
Send us the drawings, the scope and the site constraints. We will set out how we would deliver the steelwork, from shop drawings to erection.