Galata Bridge Bascule Leaf Repair
Nessac repaired the counterweight cross girders and hanger plates of the four leaves on the Galata Bridge's 80 m bascule span in Istanbul, each leaf carrying a counterweight of around 1,000 tonnes, by transferring that load through temporary girders onto the leaves' main girders.
Bascule leaf repair on the Galata Bridge
The Galata Bridge opens at its bascule span, where four steel leaves give ships entering the Golden Horn an 80 m clear opening. In 1998, cracks were found in the cross girders and hanger plates that carry the leaves' counterweights. Nessac took on the repair as a subcontractor. It prepared the method statements from the designer's repair design and carried out the repair. It also serviced the bascule's hydraulic, electrical-electronic and mechanical systems before the bridge reopened to road and marine traffic.
Girders carrying a 1,000-tonne counterweight
On the Galata Bridge bascule, each counterweight was around 1,000 tonnes of barite concrete, and the cross girders and hanger plates to be repaired were carrying it. Before any strengthening or welding could start, that load had to come off them. The damaged zones could only be reached from inside the deck, so the deck plate and the counterweight concrete had to be opened up locally. In places, the strengthening plates were 100 mm thick.
Transferring the load, then repairing
Nessac fabricated temporary transfer girders and a steel temporary support and scaffolding system inside the caisson from the −7.50 m elevation to the underside of the counterweight. The temporary girders sat on the leaf's main girders and were tied to the lower supports by tie bars run through holes in the deck. Hydraulic jacks then moved the counterweight load through the temporary girders onto the main girders. With the zone unloaded, each strengthening plate was fitted, checked by survey, welded to the approved welding procedure specification and inspected by non-destructive testing (NDT). All four leaves were worked in parallel.
The bascule opens and closes again
When the strengthening was complete, Nessac put the load back onto the main girders through the repaired cross girders and hanger plates, returning the leaves to their original loading position. The temporary system was taken down and the deck openings were welded shut. After the hydraulic, electrical-electronic and mechanical systems were serviced, the bascule went back into service in 2001.
What this project actually required
Not a generic service list — the specific capabilities exercised on this package.
Stages delivered on this project
From site works to the completed structure
More from the bridge & infrastructure record
Planning comparable bridge or infrastructure work?
Send us the drawings, the scope and the site constraints. We will set out how we would deliver the steelwork, from shop drawings to erection.