Capability · Engineering

Erection Engineering

We settle how your steel will be erected before work starts: method statements, lift plans, shop drawings and structural calculations, prepared by the team that runs the works.

Short answer
Nunteknik prepares the engineering that steel erection depends on: method statements, lift plans, programmes, shop drawings and structural calculations for temporary works. On the Fatih Sultan Mehmet Bridge we wrote a separate method statement for each crack type; on the 1915 Çanakkale Bridge, lift plans for removing around 1,400 t of temporary steelwork from the tower tops and anchor blocks.
Nunteknik · İstanbul, Türkiye
Scope

Competencies in this capability

Each competency below is delivered under the same contract and the same quality system.

Method Development

Method Development

Method statements for each item or repair type, setting sequence, lifting points and sling angles, with the programme tied to excavation, lane closures or parallel works.

Shop Drawings

Shop Drawings

Shop drawings from design drawings, assembly drawings or a 3D model, for new steel, repair plates and temporary shoring, with as-built drawings at handover.

Structural Analysis

Structural Analysis

Structural calculations for access structures and dismantling scaffolds, and capacity checks when we propose equivalent sections. Calculations we commission stay ours.

Track record

Where we applied it

Selected projects: method statements, lift plans, drawings and calculations

ProjectApplied asStandardScale
1915 Çanakkale Bridge Access StructuresShop drawings, structural calculations, methodEXC2around 113 t
1915 Çanakkale Bridge Temporary Works RemovalMethod, lift plans, scaffold calculationsaround 1,400 t removed
Fatih Sultan Mehmet Bridge Fatigue Crack RepairMethod statement per crack type, shop drawingsAASHTO/AWS D1.51,576 repairs
Bosphorus Bridge Expansion Joint ReplacementMethod, shop drawings, equivalent-section checkAASHTO/AWS D1.5around 215 t
1915 Çanakkale Bridge Expansion JointsErection method, lift plan, ITP4 × 55 t
Çorlu Steel Building and Machine TowersTower shop drawings from assembly drawings, ITPEXC3around 1,093 t

On these projects

  • Provisional acceptance on 1915 Çanakkale access structures
  • Taking-over certificate issued with no outstanding items
  • 1,576 repairs handed over under provisional acceptance
  • Equivalent sections used after capacity comparison

Inspection documents

  • Method statements and lift plans◷ pending
  • Structural calculation reports◷ pending
  • Shop and as-built drawings◷ pending

Published as cover, contents and redacted signature pages. Full ITPs, method statements and shop drawings are not published.

How we apply it

From site survey to an approved method

Five steps we follow before steel is lifted, cut or welded on your project.

SurveyWhere new steel meets existing steel, we measure each seat on site and check it against the drawings.
MethodWe write a method statement per item or repair type: sequence, lifting points, sling angles, cutting lines.
CalculateWe calculate what the design leaves to us: access structures, dismantling scaffolds, equivalent sections.
DetailWe produce shop drawings from the design drawings, assembly drawings or a 3D model.
Plan and recordWe prepare lift plans and the programme, inspect against the ITP and hand over as-built drawings.

Standards

EN ISO 14122Access geometry on 1915 Çanakkale access structures
AASHTO/AWS D1.5Welding code in Bosphorus and FSM repair methods

Certificate numbers are available on request.

FAQ

Frequently asked questions

Do you prepare the method statements yourselves?

Yes. On the Fatih Sultan Mehmet Bridge we wrote a method statement for each crack type from its approved repair detail. On the 1915 Çanakkale Bridge, our method statements and lift plans set the dismantling sequence, lifting points and sling angles for every temporary structure.

Do you carry out structural analysis in-house?

Often, yes. We prepared the structural calculations for the 1915 Çanakkale Bridge access structures and for the dismantling scaffolds on its tower tops. Where we commission a calculation, as with the façade steel of a trade centre in İkitelli, it stays under our responsibility.

Can you propose alternatives to the design sections?

Yes, with calculations. On the Bosphorus Bridge expansion joints we replaced the American sections in the design with equivalent European sections, after verifying their capacity by comparative calculations and submitting them for approval.

How do you plan heavy or restricted lifts?

Each lift is planned before it is made. The 55-tonne expansion joints on the 1915 Çanakkale Bridge went in with a 350-tonne mobile crane provided by the client; the lift plan and the operation were ours. On the tower tops, every item was split to suit the tower-top crane.

What do you hand over at the end?

Records the client can maintain the structure with. On the 1915 Çanakkale Bridge access structures the handover file held the as-built drawings and an operation and maintenance manual; on the Bosphorus Bridge expansion joints we handed over with as-built drawings.

Next Step

Let's Discuss Your Erection Method

Send us the drawings and the site constraints. We will set out the method, lifts and temporary works we would use on your project.