1915 Çanakkale Bridge Tower and Anchorage Temporary Works Removal
Nunteknik dismantled around 1,400 tonnes of temporary steelwork from the two towers and two anchor blocks of the 1915 Çanakkale Bridge, working as a subcontractor to the main contractor.
Removing the tower and anchorage temporary works
Building the 1915 Çanakkale Bridge required temporary steel structures on the towers and in the anchor blocks, and these had to be dismantled: tower-top bents, winches and their supports, welding platforms, scaffolding, catwalk anchoring beams, splay bents and cross-passages. As subcontractor to the main contractor, we wrote the dismantling method statement, carried out the dismantling, and repaired the grout and paint and applied epoxy where lugs had been cut off.
Heavy items at the tower top, and the wind
Each tower top carried four 21-tonne winches and bents made up of blocks of 14 tonnes. Our daily reports record wind affecting work on 54 days between September and early December, and on 30 of them both the day and night shifts were stood down. Dismantling at the tower tops ran on one integrated programme with the artillery shell figure enclosures we were erecting on the same towers, and work at both towers and both anchor blocks ran over the same period.
Method statement, two shifts, rope access
Our method statement set out the sequence, lifting points and guide ropes for each structure. It called for the winches and the main-span catwalk anchoring beams to be split and lowered in parts, bolts to be released with electric torque wrenches, and any bolt that would not release to be cut with oxygen. Rope access technicians removed the restraint and link plates. We commissioned the structural analysis reports for the dismantling scaffolding. Until 21 November 2022 the site ran day and night shifts.
Taken over with no missing items
We dismantled the temporary works within our scope at both towers and both anchor blocks, bringing down around 1,400 tonnes of steel, and repaired grout and paint and applied epoxy where lugs had been cut off. The main contractor's acceptance team inspected the works, and the taking-over certificate was issued on 30 January 2023 with no missing items recorded.
What this project actually required
Not a generic service list — the specific capabilities exercised on this package.
The stages we delivered on this project
Select a stage to see how it was carried out and controlled.
Engineering
Engineering and method statements, approved before work starts.
Erection
Steel erected by our own crews and, where the work calls for it, by subcontractors we manage.
From site works to the completed structure
More from the bridge & infrastructure record

1915 Çanakkale Bridge Anchor Block and Pier Access Structures

Galata Bridge Bascule Leaf Repair

Bosphorus Bridge Tower Strengthening and Damper Installation
Planning comparable bridge or infrastructure work?
Send us the drawings, the scope and the site constraints. We will set out how we would deliver the steelwork, from shop drawings to erection.