Night-time removal and lift-off of a temporary welding platform at the tower top
Projects
BridgeDelivered 2023

1915 Çanakkale Bridge Tower and Anchorage Temporary Works Removal

Nunteknik dismantled around 1,400 tonnes of temporary steelwork from the two towers and two anchor blocks of the 1915 Çanakkale Bridge, working as a subcontractor to the main contractor.

01 · The Brief

Removing the tower and anchorage temporary works

Building the 1915 Çanakkale Bridge required temporary steel structures on the towers and in the anchor blocks, and these had to be dismantled: tower-top bents, winches and their supports, welding platforms, scaffolding, catwalk anchoring beams, splay bents and cross-passages. As subcontractor to the main contractor, we wrote the dismantling method statement, carried out the dismantling, and repaired the grout and paint and applied epoxy where lugs had been cut off.

02 · Technical Challenges

Heavy items at the tower top, and the wind

Each tower top carried four 21-tonne winches and bents made up of blocks of 14 tonnes. Our daily reports record wind affecting work on 54 days between September and early December, and on 30 of them both the day and night shifts were stood down. Dismantling at the tower tops ran on one integrated programme with the artillery shell figure enclosures we were erecting on the same towers, and work at both towers and both anchor blocks ran over the same period.

03 · Our Execution

Method statement, two shifts, rope access

Our method statement set out the sequence, lifting points and guide ropes for each structure. It called for the winches and the main-span catwalk anchoring beams to be split and lowered in parts, bolts to be released with electric torque wrenches, and any bolt that would not release to be cut with oxygen. Rope access technicians removed the restraint and link plates. We commissioned the structural analysis reports for the dismantling scaffolding. Until 21 November 2022 the site ran day and night shifts.

04 · The Outcome

Taken over with no missing items

We dismantled the temporary works within our scope at both towers and both anchor blocks, bringing down around 1,400 tonnes of steel, and repaired grout and paint and applied epoxy where lugs had been cut off. The main contractor's acceptance team inspected the works, and the taking-over certificate was issued on 30 January 2023 with no missing items recorded.

Capabilities Applied

What this project actually required

Not a generic service list — the specific capabilities exercised on this package.

Method DevelopmentStructural AnalysisQuality Plan & ITPSteel DismantlingHeavy Crane LiftingRope Access & Work at Height
Execution & Assurance

The stages we delivered on this project

Select a stage to see how it was carried out and controlled.

1
EngineeringApproved method
2
ErectionOwn crews first

Engineering

Engineering and method statements, approved before work starts.

Method statement approval