Erection adds stability with every piece: each member is bolted into a frame that is stiffer than it was a minute ago. Dismantling takes it away. Every piece that comes out leaves the rest of the structure in a state it was never designed for.
That is why we do not plan dismantling by reading the erection sequence backwards. The sequence is worked out on its own, piece by piece, and written down before anything is released.
The crane sizes the piece, not the drawing
On the 1915 Çanakkale Bridge, the temporary steelwork used to build the bridge had to come off the two tower tops, the upper cross beams joining them and the two anchor blocks once the bridge was complete: around 1,400 tonnes of bents, winches, catwalk anchoring beams, welding platforms and cross-passages.
Everything on the tower tops had to come down with the tower-top crane. Each tower carried four winches weighing 21 tonnes each and bent blocks of up to 14 tonnes, and wind over the strait stopped lifting outright. So the drawing did not decide how a structure came apart; the crane did. We lowered the winches in three parts after separating the motor and the lifting beam, and the main-span catwalk anchoring beams in ten.
For every structure we prepared a method statement and a lift plan, setting out the dismantling sequence, the lifting points and the sling angles. Both towers and both anchorages were worked at the same time, on day and night shifts.
Connections do not come apart the way they went together
A bolt that went in with a torque wrench does not always come out with one. On the Çanakkale tower tops we released bolts with torque wrenches and the anchor lug nuts with hydraulic jacks, and oxy-cut the connections that would not release. Rope access technicians removed the connection plates that could not be reached any other way.
Welds are harder. On the 15 July Martyrs Bridge (Bosphorus Bridge), replacing the expansion joints meant removing existing welds by carbon arc gouging and plasma cutting the deck plate and ribs on site, before the new deck section could be bolted and welded to the steel that stayed.
The structure stays in use
Most of what we dismantle is part of something still working. On the Bosphorus Bridge joints, the bridge stayed open to traffic. We split the work into four phases and finished in 75 days, closing only two of six lanes at a time.
At a metals plant in Çorlu, production did not stop while we strengthened and raised part of a steel building. We removed 55 tonnes of roof trusses and 21.5 tonnes of crane rails, which left one bay without its overhead crane until the works were finished. While that bay had no crane, our mobile cranes and platforms supported the plant's line maintenance. We re-erected the rails at +42.00 m.
The piece that comes out is the survey for the piece that goes in
At the four tower-deck junctions of the Bosphorus Bridge, the plates and girders of the widened walkway section around the tower had to be replaced with new steel that fitted the existing bridge exactly.
We worked from a platform hung under the deck at +58.00, raised by ground winches and re-rigged at each of the four points, during night lane closures. After removing the hinged plates, we lowered the main plate together with its girders in one piece and sent it to the shop. The new piece was fabricated to those dimensions, with all welding on the main connection done in the shop. On site we set it in place in one piece and made the main connection with bolts. Secondary welds were made on site, and at all four points they passed magnetic particle testing.
Sometimes the same steel goes back up
At the cut-and-cover depot excavation of the Kabataş–Mahmutbey Metro Line, the steel walers and Ø610 mm strut pipes holding the excavation walls apart were erected level by level as the dig advanced: 208 tonnes in all. For the second stage, the same steel was taken out of the first stage and re-erected in the second work area, with removal and re-erection running on the same days.
Dismantling for reuse is a sequencing problem. A piece comes out only when the next work area is ready to take it.
What we do not do
We dismantle structural steel. Concrete demolition, whole-building demolition and the removal of anything other than steel are not work we take on. On the metro depot, the shoring design and the excavation were outside our scope as well.
The record
On the 1915 Çanakkale Bridge, the temporary structures on both tower tops and in both anchor blocks were removed. Where connections had been cut, we made grout and epoxy repairs, and paint repairs on the tower faces. The main contractor's acceptance team inspected the works, and the taking-over certificate was issued on 30 January 2023 with no outstanding items.
Send us the drawings and the site constraints. We will set out how we would take the steel down.