Completed steel strut and waler system in the cut-and-cover excavation of the Kabataş–Mahmutbey Metro Line depot area, Istanbul
Projects
InfrastructureDelivered 2018

Kabataş–Mahmutbey Metro Depot Strut and Waler Erection

Nunteknik erected around 164 tonnes of steel walers and Ø610 mm strut pipes as excavation advanced in the cut-and-cover pit at the depot site of the Kabataş–Mahmutbey Metro Line in Istanbul, then removed the first-stage steel and re-erected it for the second stage.

01 · The Brief

Steel shoring supports for a metro depot excavation

The cut-and-cover excavation at the depot site of the Kabataş–Mahmutbey Metro Line was to be shored by steel walers fixed to bored piles and strut pipes bracing the excavation walls against each other. As a subcontractor, we supplied the HEA400 walers and Ø610 × 16 mm strut pipes, had them fabricated in a partner shop and erected them. We also removed the first-stage steel and re-erected it for the second stage. The shoring design, the excavation and the concrete works were outside our scope.

02 · Technical Challenges

Erected twice, in step with the excavation

Steel erection and excavation took turns in the same pit. Each support level had to go in once the dig reached that level, and the next excavation stage could start only once it was in place. Supports were to be installed at two levels, +122.90 m and +126.90 m, with struts up to 9.8 m long and around 2.5 t per piece connected to the walers. The same steel was to be used twice: the first-stage walers and struts had to be removed and re-erected for the second stage.

03 · Our Execution

Brackets, walers and struts, level by level

We prepared the shop drawings for the walers and strut pipes. Level by level, we erected the brackets, the walers, each built from three HEA400 sections, and the strut pipes, fixing the walers to the bored piles and connecting the struts to the walers through their end plates. We used a mobile crane for the lifts. The struts and walers removed from the first stage were re-erected in the second stage. On 6 May 2018 we removed 5 struts and 9 waler members and erected 4 struts in a single day.

04 · The Outcome

Excavation support erected in two stages

We completed the work in June 2018, and the steel we erected supported the excavation in both stages. The measured quantities for the progress payment show 42 waler members totalling around 110 tonnes and 29 strut pipes totalling around 54 tonnes.

Capabilities Applied

What this project actually required

Not a generic service list — the specific capabilities exercised on this package.

Shop DrawingsFabrication ManagementSteel ErectionSteel DismantlingWelded ConnectionsBolted Connections
Execution & Assurance

The stages we delivered on this project

Select a stage to see how it was carried out and controlled.

1
EngineeringApproved method
2
FabricationShop fabrication
3
ErectionOwn crews first

Engineering

Engineering and method statements, approved before work starts.

Method statement approval

Project Documents — available on request

EN 1090EN ISO 9606