Rumeli Hisarüstü Funicular Station Steel Strut Shoring
As a subcontractor, Nunteknik supplied the 864 mm diameter steel pipe struts for the deep station pit at Rumeli Hisarüstü on the Rumeli Hisarüstü–Aşiyan Funicular Line, and erected them level by level as the excavation deepened.
Steel strut shoring for a funicular station pit
Rumeli Hisarüstü station on the Rumeli Hisarüstü–Aşiyan Funicular Line was built inside a deep excavation retained by bored-pile walls. As the excavation deepened, steel pipe struts had to prop the opposing walls against each other. Our subcontract covered the supply and erection of the struts (864 mm OD, 16 mm wall, S355JR) and their bearing plates, together with the reinforced concrete waler beams and the prestressed ground anchors. A subcontractor we managed installed the anchors and did the waler labour.
Staged excavation, struts over 20 m long
Every level followed the same order: cast the waler beam, install the anchors, place the struts, and only then dig down to the next level. No strut could go in before the waler concrete had reached its design strength. The longest strut was 20.86 m and weighed around 7 tonnes, and each one had to be lowered past the struts already in place above it.
Shop-fabricated, bolted on site
We wrote the method statement for the steel shoring and produced the shop drawings for the strut pipes. A partner shop fabricated the pipes and their end flanges under our responsibility. On site, we waited at each level for the waler concrete to reach design strength. We then lowered the struts into the pit by mobile crane and bolted them to the bearing plates on the waler.
Four strut levels at Hisarüstü, two at Aşiyan
Our January 2018 progress claim records strut erection on three levels at Rumeli Hisarüstü station. By May 2018 we had completed the third level, erected a fourth at Hisarüstü and installed two strut levels at Aşiyan station on the same line. Material certificates for the plates and bolts are on file.
What this project actually required
Not a generic service list — the specific capabilities exercised on this package.
The stages we delivered on this project
Select a stage to see how it was carried out and controlled.
Engineering
Engineering and method statements, approved before work starts.
Fabrication
Steel fabricated in EN 1090 certified partner shops under our quality control, to approved welding procedures (WPS).
Erection
Steel erected by our own crews and, where the work calls for it, by subcontractors we manage.
From the fabrication shop to the completed structure