Kennedy Avenue Pedestrian Overpasses: Concrete Works and Steel Stairs
As a subcontractor on the Eurasia Tunnel project in Istanbul, Nunteknik undertook the reinforced concrete works for four pedestrian overpasses on Kennedy Avenue and supplied and erected approximately 134 tonnes of galvanised steel stairs and railings.
Concrete works and steel stairs for four overpasses
Four pedestrian overpasses on Kennedy Avenue were part of the Eurasia Tunnel (Istanbul Strait Road Tube Crossing) project. Each had two spans, three piers, two lifts and four steel staircases in total, serving both sides of the road. We took on the reinforced concrete works for the piers, pier caps, landings and deck slab, and the supply, fabrication and erection of the steel stairs and railings. Our scope also included demolishing a masonry retaining wall in Samatya and rebuilding it in reinforced concrete.
3 mm bearing tolerance on a shared site
The specified tolerances were 3 mm on the bearing levels for the precast girders and ±10 mm on foundation top levels. Girder erection, waterproofing and the panoramic lifts were carried out by other contractors, and the deck slab had to wait for the girders. The steelwork would arrive galvanised and painted, so touching up paint damaged during erection was part of our scope.
Cast-in anchors fixed before concreting
Our subcontractor carried out the concrete placement, reinforcement fixing and formwork for the foundations, piers and retaining wall under our management. The cast-in anchors for the steel stairs were fixed in the formwork before concreting, and the register contains 129 pre-concreting inspection records. We produced the shop drawings and had the stairs and railings fabricated in an EN 1090 certified partner shop. They were blast-cleaned, hot-dip galvanised and painted, and our own crews erected them with bolted and welded connections.
1,367 m³ of concrete, 134 tonnes of steel
The payment records list 1,367 m³ of structural concrete and 202 tonnes of reinforcement for the four overpasses and the retaining wall, and 80 elastomeric bearings for the overpasses. We erected approximately 134 tonnes of galvanised stairs and railings, including 867 m of railing. The as-built set for the four overpasses runs to 65 drawings dated November 2016. The completion payment certificate was issued on 31 December 2016.
What this project actually required
Not a generic service list — the specific capabilities exercised on this package.
The stages we delivered on this project
Select a stage to see how it was carried out and controlled.
Engineering
Engineering and method statements, approved before work starts.
Fabrication
Steel fabricated in EN 1090 certified partner shops under our quality control, to approved welding procedures (WPS).
Erection
Steel erected by our own crews and, where the work calls for it, by subcontractors we manage.
From the fabrication shop to the completed structure
More from the bridge & infrastructure record
Planning comparable bridge or infrastructure work?
One contract. Steel to finish. Tell us the scope and we'll come back to you under single-point responsibility.