Completed galvanized steel track supports along the funicular line inside the station
Projects
InfrastructureDelivered 2021

Rumeli Hisarüstü–Aşiyan Funicular Line Steel Track Supports

For both stations of the Rumeli Hisarüstü–Aşiyan Funicular Line, Nunteknik had around 34 tonnes of steel track beams and supports fabricated to EXC3 under the system manufacturer's drawings, then delivered them galvanised and erected them with its own crews.

01 · The Brief

Steel track supports for two funicular stations

The top and bottom stations of the line needed steel track beams and supports to carry the funicular rails. The beams, supports, connection brackets and shim plates were to follow the funicular system manufacturer's drawing set. As a subcontractor, we were responsible for the supply of sections and plate, fabrication, hot-dip galvanising and delivery to site, along with high-strength bolt sets, anchors and 16 elastomeric bearings. Erection was added later under a second contract.

02 · Technical Challenges

EXC3 requirements and sections sourced abroad

The drawings specified EN 1090 Execution Class EXC3 and welding to the manufacturer's welding standard, with 100% visual inspection of the welds. The longest track beam was 11.6 m long and weighed 2,158 kg. The track beams were HEB450 sections that had to be sourced from abroad. The parts lists also included shim plates 1, 2, 5 and 10 mm thick.

03 · Our Execution

From parts lists to nesting, galvanising to site

We turned the manufacturer's parts lists into our own quantity and material lists and nested the plate parts by thickness. We sourced the HEB450 sections from abroad and managed fabrication at a partner shop. The galvanised parts went to site in batches, and our crews erected the beams and supports at both stations. On a later additional request, we had a further 234 shim plates, 5 mm thick, fabricated and delivered.

04 · The Outcome

Around 34 tonnes of track supports, two stations

The track beams and supports for the top and bottom stations were delivered galvanised and erected. According to the parts lists, the fabricated steel came to around 34 tonnes. The galvanising measurement report records coating thickness above the EN ISO 1461 requirement at every point measured in a 3.9-tonne batch.

Capabilities Applied

What this project actually required

Not a generic service list — the specific capabilities exercised on this package.

Fabrication ManagementProtective CoatingSteel ErectionBolted Connections
Execution & Assurance

The stages we delivered on this project

Select a stage to see how it was carried out and controlled.

1
FabricationShop fabrication
2
ErectionOwn crews first

Fabrication

Steel fabricated in EN 1090 certified partner shops under our quality control, to approved welding procedures (WPS).

EN 1090 shop · WPS

Project Documents — available on request

EN 1090EN ISO 9606
Project Gallery

From the fabrication shop to the completed structure

Planning comparable bridge or infrastructure work?

One contract. Steel to finish. Tell us the scope and we'll come back to you under single-point responsibility.