The renewed expansion joint on the suspension bridge deck, open to traffic, with the tower behind
Projects
BridgeDelivered 2017

Bosphorus Bridge Expansion Joint Replacement

Working under live traffic, Nunteknik removed and replaced the expansion joints at the Ortaköy and Beylerbeyi ends of the 15 July Martyrs Bridge (Bosphorus Bridge) in four phases and installed around 215 tonnes of strengthening steel in the deck and viaducts.

01 · The Brief

Joint replacement and deck strengthening at both ends

At both ends of the Bosphorus Bridge the existing expansion joints were to give way to new modular joints, with the box girder end diaphragm and the deck and rib panels replaced at the joint zones. As a subcontractor, we removed the old joints and installed the new ones, which were supplied by their manufacturer. We supplied and erected the strengthening steel, fabricated in a partner shop under our responsibility. Shop and erection drawings, method statements and as-built drawings were in our scope.

02 · Technical Challenges

Two lanes at a time on an open bridge

The site work ran in four phases over 75 days with the bridge open to traffic, each phase closing two lanes. The joint, deck panel and diaphragm had to be replaced within that two-lane width. That meant removing existing welds, cutting deck plate, longitudinal ribs and diaphragm on site, and connecting the new parts to the existing steel with bolts and welds. Welding was governed by AASHTO/AWS D1.5, the bridge welding code, and subject to non-destructive testing.

03 · Our Execution

Remove, replace the deck section, set the joint

Each phase ran in the same order. We gouged out the welds of the old joint by air carbon arc, lifted the joint and its beams out with a mobile crane, and plasma-cut the deck plate and ribs. We then placed, bolted and welded the new deck section and finally installed the new joint. Third-party inspection firms carried out the NDT. The design called for American W sections. We used equivalent European sections instead, showed the equivalence by comparing load capacities, and the comparison was approved.

04 · The Outcome

New joints installed, final acceptance

The new joints at Ortaköy and Beylerbeyi were installed, and on as-built measurement the strengthening steel came to around 215 tonnes. We handed the work over with as-built drawings. After the client and Nunteknik inspected the completed work together on site, the final acceptance certificate was signed in May 2018, with nothing recorded that would prevent acceptance.

Capabilities Applied

What this project actually required

Not a generic service list — the specific capabilities exercised on this package.

Method DevelopmentShop DrawingsNon-Destructive TestingFabrication ManagementProtective CoatingSteel ErectionSteel DismantlingWelded ConnectionsBolted ConnectionsHeavy Crane Lifting
Execution & Assurance

The stages we delivered on this project

Select a stage to see how it was carried out and controlled.

1
EngineeringApproved method
2
FabricationShop fabrication
3
ErectionOwn crews first
4
TestingWeld inspection

Engineering

Engineering and method statements, approved before work starts.

Method statement approval

Project Documents — available on request

EN 1090EN ISO 9606NDT
Project Gallery

From the fabrication shop to the completed structure

Planning comparable bridge or infrastructure work?

Send us the drawings, the scope and the site constraints. We will set out how we would deliver the steelwork, from shop drawings to erection.