Bosphorus Bridge Tower Strengthening and Damper Installation
Nunteknik erected 412 tonnes of stiffeners and diaphragms inside the four tower legs of the 15 July Martyrs Bridge (Bosphorus Bridge) in Istanbul, from +4.50 m up to +149.25 m, and installed four viscous dampers between the towers and the deck.
Tower strengthening and damper installation, Bosphorus Bridge
The major repair of the Bosphorus Bridge required longitudinal stiffeners and transverse diaphragms to increase the buckling stiffness of the tower legs. With the hangers changed from inclined to vertical, we also needed viscous dampers between the towers and the deck. As a subcontractor, we prepared the detailed design and method statements, had the client-supplied steel fabricated in partner shops under our management, and erected it. Under the same contract, we also repaired 611 fatigue cracks in the deck.
From +4.50 m to +149.25 m, a different access at each level
The work ran from the base of each tower leg up to +149.25 m, and every level needed its own access. The stiffeners went in between +4.50 m and +27.50 m, brought in through a lower door 1.98 m high and 1.25 m wide. The diaphragms followed at +42.50 to +50.00 m, +62.35 to +71.80 m and +149.25 m. The tower legs were closed steel boxes, and the old paint at the bolting locations contained lead, so we removed it under a dedicated lead paint removal procedure.
A platform and a method for each level
We removed the entrance lift cage, set up a monorail winch circling the tower interior at +30.375 m and erected the stiffeners top-down from interior scaffolding. We revised the method to drill the tower plate from inside, not outside, with the flanges shop-drilled. We stripped the lead paint by dust-free vacuum blasting and tightened the M22 preloaded bolting assemblies by the turn-of-nut method to a minimum preload of 176 kN. At +149.25 m we worked from a platform at +147 m, with rope access technicians we engaged holding the bolt heads outside. Dampers went up on a platform hung from the footwalk.
412 t of steel, four dampers, final acceptance
We installed 411,963 kg of stiffeners and diaphragms in the four tower legs, 740 kg of end diaphragm strengthening in the box girder and the four viscous dampers. The deck crack repairs were recorded in UT, VT and radiographic reports from a third-party inspection company. Nunteknik prepared the as-built drawings and handed them over to the client. The final acceptance certificate was signed in July 2017, recording no obstacle to acceptance.
What this project actually required
Not a generic service list — the specific capabilities exercised on this package.
Every stage from steel to handover sits with us
One continuous chain of responsibility — and each phase independently verified. Select a phase to see how it was controlled.
Engineering
Engineering and method statements, approved before work starts.
Fabrication
Steel fabricated in EN 1090 certified partner shops under our quality control, to approved welding procedures (WPS).
Erection
Steel erected by our own crews and, where the work calls for it, by subcontractors we manage.
Testing
Non-destructive testing of critical welds.
Handover
Commissioning and a complete as-built documentation dossier, handed over under single-point responsibility.
From site works to the completed structure
More from the bridge & infrastructure record

1915 Çanakkale Bridge Anchor Block and Pier Access Structures

Galata Bridge Bascule Leaf Repair

Fatih Sultan Mehmet Bridge Orthotropic Deck Crack Repair
Planning comparable bridge or infrastructure work?
Send us the drawings, the scope and the site constraints. We will set out how we would deliver the steelwork, from shop drawings to erection.