Fatih Sultan Mehmet Bridge Orthotropic Deck Crack Repair
Working from inside the deck while traffic kept crossing above, Nunteknik repaired 1,576 fatigue cracks of 21 types in the orthotropic steel deck of the Fatih Sultan Mehmet Bridge in Istanbul, and the work passed provisional acceptance.
Fatigue crack repair inside an orthotropic deck
Fatigue cracks had formed in the rib, deck plate and internal diaphragm welds of the Fatih Sultan Mehmet Bridge's orthotropic box girder deck. Working as a subcontractor, we were to repair each crack according to its type, have the repair plates fabricated and install them, and provide the shop drawings, erection drawings, method statements and as-built drawings.
A live bridge and a crack list that grew during the work
The bridge stayed open to traffic throughout the repairs. Where a repair type cut an opening in a rib, the design required each opening to be cut and its strengthening plate installed within a single overnight closure of the lane above. The contract listed 1,386 cracks, revised by addendum to 1,382, and dye-penetrant testing then found 194 more. The deck interior had just been fully repainted and carried the dehumidification system cabling. Both had to be protected, and welding had to comply with AASHTO/AWS D1.5.
One method statement per crack type
We wrote a separate method statement for each crack type, based on its approved repair detail. On the weld-repair types, dye-penetrant testing located the end of the crack. We then removed the cracked weld mechanically, prepared the joint for a full-penetration weld and re-welded after preheating to 120 °C. Each rib opening was cut and plated within the same night lane closure. At the diaphragms we core drilled 60 mm holes on either side of the rib and plasma cut to a template. Non-destructive testing was carried out no earlier than 24 hours after welding.
1,576 repairs, provisionally accepted
We completed all 1,576 repairs across 21 crack types with the bridge in service. The provisional acceptance certificate was signed in November 2017 after a joint site inspection and records nothing to prevent acceptance.
What this project actually required
Not a generic service list — the specific capabilities exercised on this package.
The stages we delivered on this project
Select a stage to see how it was carried out and controlled.
Engineering
Engineering and method statements, approved before work starts.
Fabrication
Steel fabricated in EN 1090 certified partner shops under our quality control, to approved welding procedures (WPS).
Erection
Steel erected by our own crews and, where the work calls for it, by subcontractors we manage.
Testing
Non-destructive testing of critical welds, with independent third-party (TPI) inspection sign-off.
From the fabrication shop to the completed structure
More from the bridge & infrastructure record
Planning comparable bridge or infrastructure work?
Send us the drawings, the scope and the site constraints. We will set out how we would deliver the steelwork, from shop drawings to erection.