The tower and steel deck of the Fatih Sultan Mehmet Bridge in Istanbul; the repair works were carried out inside this deck.
Projects
BridgeDelivered 2017

Fatih Sultan Mehmet Bridge Orthotropic Deck Crack Repair

Working from inside the deck while traffic kept crossing above, Nunteknik repaired 1,576 fatigue cracks of 21 types in the orthotropic steel deck of the Fatih Sultan Mehmet Bridge in Istanbul, and the work passed provisional acceptance.

01 · The Brief

Fatigue crack repair inside an orthotropic deck

Fatigue cracks had formed in the rib, deck plate and internal diaphragm welds of the Fatih Sultan Mehmet Bridge's orthotropic box girder deck. Working as a subcontractor, we were to repair each crack according to its type, have the repair plates fabricated and install them, and provide the shop drawings, erection drawings, method statements and as-built drawings.

02 · Technical Challenges

A live bridge and a crack list that grew during the work

The bridge stayed open to traffic throughout the repairs. Where a repair type cut an opening in a rib, the design required each opening to be cut and its strengthening plate installed within a single overnight closure of the lane above. The contract listed 1,386 cracks, revised by addendum to 1,382, and dye-penetrant testing then found 194 more. The deck interior had just been fully repainted and carried the dehumidification system cabling. Both had to be protected, and welding had to comply with AASHTO/AWS D1.5.

03 · Our Execution

One method statement per crack type

We wrote a separate method statement for each crack type, based on its approved repair detail. On the weld-repair types, dye-penetrant testing located the end of the crack. We then removed the cracked weld mechanically, prepared the joint for a full-penetration weld and re-welded after preheating to 120 °C. Each rib opening was cut and plated within the same night lane closure. At the diaphragms we core drilled 60 mm holes on either side of the rib and plasma cut to a template. Non-destructive testing was carried out no earlier than 24 hours after welding.

04 · The Outcome

1,576 repairs, provisionally accepted

We completed all 1,576 repairs across 21 crack types with the bridge in service. The provisional acceptance certificate was signed in November 2017 after a joint site inspection and records nothing to prevent acceptance.

Capabilities Applied

What this project actually required

Not a generic service list — the specific capabilities exercised on this package.

Method DevelopmentShop DrawingsWelding Procedure QualificationNon-Destructive TestingFabrication ManagementProtective CoatingSteel ErectionWelded ConnectionsBolted ConnectionsThird-Party Inspection
Execution & Assurance

The stages we delivered on this project

Select a stage to see how it was carried out and controlled.

1
EngineeringApproved method
2
FabricationShop fabrication
3
ErectionOwn crews first
4
TestingWeld inspection

Engineering

Engineering and method statements, approved before work starts.

Method statement approval

Project Documents — available on request

EN 1090EN ISO 9606TPI · NDT
Project Gallery

From the fabrication shop to the completed structure

Planning comparable bridge or infrastructure work?

Send us the drawings, the scope and the site constraints. We will set out how we would deliver the steelwork, from shop drawings to erection.