A modular expansion joint guided by tag line during the crane lift
Projects
BridgeDelivered 2022

1915 Çanakkale Bridge Expansion Joint Installation

On the 1915 Çanakkale Bridge, Nunteknik installed the four 55-tonne modular expansion joints between the suspension deck and the approach viaducts, setting, welding and bolting each 16.19 m unit on site.

01 · The Brief

Site installation of four factory-built joints

The suspension section of the 1915 Çanakkale Bridge carries four expansion joints, two at each end of the deck over the European and Asian side-span piers. The manufacturer fabricated the joints and delivered them complete. Our contract covered the site work from there: loading at the laydown area, transport, lifting, positioning and presetting, welding of the joints and cover plates, bolt tightening, and corrosion protection of the weld areas.

02 · Technical Challenges

Heavy units, thick plate, confined space

Each joint weighed 55 tonnes and measured 16.19 m. Its end plate had to sit on the steel deck at a set distance of 1,485 mm from a diaphragm, with the joint opening adjusted to the temperature at the time of installation. Most welds were in 35–50 mm S460M plate and were required to transfer no residual stress into the bridge sections. The stiffener-to-end-plate welds lay beneath the cover plate in a confined space, reached through the bottom manholes and a 150 mm access cut-out.

03 · Our Execution

Temperature-based presetting, designer-set weld sequence

The 350-tonne mobile crane was provided to us. We prepared the lift plan and lowered the joints into place, aligned each one with hydraulic jacks and preset its opening to the temperature at the time of installation. A survey firm we engaged took the position and level measurements. The weld sequence followed the bridge designer's response to a technical query, starting at the end plate and finishing with bolt tightening. We welded to our own WPSs (processes 136 and 136+121) with fans ventilating the confined space. An NDT contractor carried out VT, MT and UT for us.

04 · The Outcome

Four joints in place, weld and bolt records for each

All four joints and their cover plates were welded in, the bolts tightened and the weld areas painted. Interim payment certificate no. 1 shows every bill-of-quantities item at 100% cumulative. Each joint has a fit-up report, weld log, NDT reports and a bolt-tightening report, and two paint inspection reports cover all four. The records follow the inspection points of our ITP, and the inspection requests for all four joints were closed.

Capabilities Applied

What this project actually required

Not a generic service list — the specific capabilities exercised on this package.

Method DevelopmentQuality Plan & ITPWelding Procedure QualificationNon-Destructive TestingSteel ErectionWelded ConnectionsBolted ConnectionsHeavy Crane LiftingLift PlanningProtective Coating
Execution & Assurance

The stages we delivered on this project

Select a stage to see how it was carried out and controlled.

1
EngineeringApproved method
2
ErectionOwn crews first

Engineering

Engineering and method statements, approved before work starts.

Method statement approval
Project Gallery

From site works to the completed structure

Planning comparable bridge or infrastructure work?

Send us the drawings, the scope and the site constraints. We will set out how we would deliver the steelwork, from shop drawings to erection.