1915 Çanakkale Bridge Expansion Joint Installation
On the 1915 Çanakkale Bridge, Nunteknik installed the four 55-tonne modular expansion joints between the suspension deck and the approach viaducts, setting, welding and bolting each 16.19 m unit on site.
Site installation of four factory-built joints
The suspension section of the 1915 Çanakkale Bridge carries four expansion joints, two at each end of the deck over the European and Asian side-span piers. The manufacturer fabricated the joints and delivered them complete. Our contract covered the site work from there: loading at the laydown area, transport, lifting, positioning and presetting, welding of the joints and cover plates, bolt tightening, and corrosion protection of the weld areas.
Heavy units, thick plate, confined space
Each joint weighed 55 tonnes and measured 16.19 m. Its end plate had to sit on the steel deck at a set distance of 1,485 mm from a diaphragm, with the joint opening adjusted to the temperature at the time of installation. Most welds were in 35–50 mm S460M plate and were required to transfer no residual stress into the bridge sections. The stiffener-to-end-plate welds lay beneath the cover plate in a confined space, reached through the bottom manholes and a 150 mm access cut-out.
Temperature-based presetting, designer-set weld sequence
The 350-tonne mobile crane was provided to us. We prepared the lift plan and lowered the joints into place, aligned each one with hydraulic jacks and preset its opening to the temperature at the time of installation. A survey firm we engaged took the position and level measurements. The weld sequence followed the bridge designer's response to a technical query, starting at the end plate and finishing with bolt tightening. We welded to our own WPSs (processes 136 and 136+121) with fans ventilating the confined space. An NDT contractor carried out VT, MT and UT for us.
Four joints in place, weld and bolt records for each
All four joints and their cover plates were welded in, the bolts tightened and the weld areas painted. Interim payment certificate no. 1 shows every bill-of-quantities item at 100% cumulative. Each joint has a fit-up report, weld log, NDT reports and a bolt-tightening report, and two paint inspection reports cover all four. The records follow the inspection points of our ITP, and the inspection requests for all four joints were closed.
What this project actually required
Not a generic service list — the specific capabilities exercised on this package.
The stages we delivered on this project
Select a stage to see how it was carried out and controlled.
Engineering
Engineering and method statements, approved before work starts.
Erection
Steel erected by our own crews and, where the work calls for it, by subcontractors we manage.
From site works to the completed structure
More from the bridge & infrastructure record
Planning comparable bridge or infrastructure work?
Send us the drawings, the scope and the site constraints. We will set out how we would deliver the steelwork, from shop drawings to erection.