Repair inside the orthotropic deck of the 15 July Martyrs (Bosphorus) Bridge: tightening bolts on splice plates at a rib-to-crossbeam joint, Istanbul
Projects
BridgeDelivered 2020

Bosphorus Bridge Orthotropic Deck Crack Repair

Nunteknik repaired 59 fatigue cracks of eight types in the orthotropic steel deck of the 15 July Martyrs Bridge (Bosphorus Bridge) in Istanbul, finishing 33 days after contract signature against a 60-day contract period.

01 · The Brief

Fatigue cracks in a box girder deck

The orthotropic box girder deck of the Bosphorus Bridge had 58 fatigue cracks spread over 46 compartments. They were in the welds between the longitudinal ribs and the deck plate, at rib splices and at internal diaphragm connections. Our scope as subcontractor covered repairing each crack according to its type and preparing the method statements. We also had the strengthening and splice plates fabricated, installed them, and repainted the repaired areas.

02 · Technical Challenges

Eight crack types, inside the deck

The cracks fell into eight types, and the repair detail changed with the type. Some were to be repaired by welding alone. Others needed a hand access hole and, after welding, a bolted strengthening plate. The repairs were inside the box girder, in its compartments, and the scaffolding was ours to provide. The contract allowed 60 calendar days, mobilisation included.

03 · Our Execution

Method statements for five crack types

We prepared method statements for five of the eight types: three repaired by welding alone and two with bolted plates. They called for the cracked weld to be removed mechanically and re-welded after preheating to 120 °C, with non-destructive testing at least 24 hours after welding. On the plated types we cut the hand access hole, ground the weld beneath the plate, drilled the plate holes, and fitted and torqued the bolts. We prepared and repainted the affected surfaces.

04 · The Outcome

59 repairs, provisionally accepted

The repairs were finished on 15 July 2020, 33 days after contract signature. The contract listed 58 cracks; one more was found during the works, and the provisional acceptance certificate records 59 repairs across eight types. The magnetic particle test report of 26 June 2020 accepted all 19 marked locations. The provisional acceptance certificate, signed after a joint site inspection, records no obstacle to acceptance.

Capabilities Applied

What this project actually required

Not a generic service list — the specific capabilities exercised on this package.

Method DevelopmentThird-Party InspectionNon-Destructive TestingFabrication ManagementProtective CoatingSteel ErectionWelded ConnectionsBolted Connections
Execution & Assurance

The stages we delivered on this project

Select a stage to see how it was carried out and controlled.

1
EngineeringApproved method
2
FabricationShop fabrication
3
ErectionOwn crews first
4
TestingWeld inspection

Engineering

Engineering and method statements, approved before work starts.

Method statement approval

Project Documents — available on request

EN 1090EN ISO 9606NDT
Project Gallery

From site works to the completed structure

Planning comparable bridge or infrastructure work?

Send us the drawings, the scope and the site constraints. We will set out how we would deliver the steelwork, from shop drawings to erection.