Bosphorus Bridge Orthotropic Deck Crack Repair
Nunteknik repaired 59 fatigue cracks of eight types in the orthotropic steel deck of the 15 July Martyrs Bridge (Bosphorus Bridge) in Istanbul, finishing 33 days after contract signature against a 60-day contract period.
Fatigue cracks in a box girder deck
The orthotropic box girder deck of the Bosphorus Bridge had 58 fatigue cracks spread over 46 compartments. They were in the welds between the longitudinal ribs and the deck plate, at rib splices and at internal diaphragm connections. Our scope as subcontractor covered repairing each crack according to its type and preparing the method statements. We also had the strengthening and splice plates fabricated, installed them, and repainted the repaired areas.
Eight crack types, inside the deck
The cracks fell into eight types, and the repair detail changed with the type. Some were to be repaired by welding alone. Others needed a hand access hole and, after welding, a bolted strengthening plate. The repairs were inside the box girder, in its compartments, and the scaffolding was ours to provide. The contract allowed 60 calendar days, mobilisation included.
Method statements for five crack types
We prepared method statements for five of the eight types: three repaired by welding alone and two with bolted plates. They called for the cracked weld to be removed mechanically and re-welded after preheating to 120 °C, with non-destructive testing at least 24 hours after welding. On the plated types we cut the hand access hole, ground the weld beneath the plate, drilled the plate holes, and fitted and torqued the bolts. We prepared and repainted the affected surfaces.
59 repairs, provisionally accepted
The repairs were finished on 15 July 2020, 33 days after contract signature. The contract listed 58 cracks; one more was found during the works, and the provisional acceptance certificate records 59 repairs across eight types. The magnetic particle test report of 26 June 2020 accepted all 19 marked locations. The provisional acceptance certificate, signed after a joint site inspection, records no obstacle to acceptance.
What this project actually required
Not a generic service list — the specific capabilities exercised on this package.
The stages we delivered on this project
Select a stage to see how it was carried out and controlled.
Engineering
Engineering and method statements, approved before work starts.
Fabrication
Steel fabricated in EN 1090 certified partner shops under our quality control, to approved welding procedures (WPS).
Erection
Steel erected by our own crews and, where the work calls for it, by subcontractors we manage.
Testing
Non-destructive testing of critical welds.
From site works to the completed structure
More from the bridge & infrastructure record
Planning comparable bridge or infrastructure work?
Send us the drawings, the scope and the site constraints. We will set out how we would deliver the steelwork, from shop drawings to erection.