Bosphorus Bridge
Opened in 1973, the Bosphorus Bridge (15 July Martyrs Bridge) was the first suspension bridge to link Europe and Asia, with a 1,074 m main span. From the towers to the deck, we have carried out strengthening, repair and replacement works across the bridge.
The work in brief
Nunteknik carried out four separate packages on the 15 July Martyrs Bridge (Bosphorus Bridge) in Istanbul, each as a subcontractor.
In the major repair of the bridge we erected 412 tonnes of stiffeners and diaphragms inside the four tower legs, from +4.50 m up to +149.25 m, and installed four viscous dampers between the towers and the deck. Under the same contract we repaired 611 fatigue cracks in the deck. We replaced the expansion joints at the Ortaköy and Beylerbeyi ends in four phases over 75 days with the bridge open to traffic, and installed around 215 tonnes of strengthening steel in the deck and viaducts. The new joints were supplied by their manufacturer. At the four tower-deck junctions we removed the plates and girders of the widened walkway sections around the towers in night lane closures and erected new steel fabricated to the measured dimensions of the old. In 2020 we repaired 59 fatigue cracks of eight types in the orthotropic steel deck, finishing 33 days after contract signature against a 60-day contract period.
The final acceptance certificates were signed in July 2017 for the tower works, in May 2018 for the expansion joints and in March 2021 for the tower-deck junctions. The deck crack repair closed with a provisional acceptance certificate.
Where on the bridge we worked
Each number marks one job. Point at a number or a row to see every place it was done.
Swipe sideways → · Lengths to scale, heights exaggerated 2.5×; schematic, not for taking dimensions. Sources: Structurae; Wikipedia; Alexandria Eng. J. 2023; IABSE 2020.
- Tower Strengthening and Damper Installation
- Expansion Joint Replacement
- Orthotropic Deck Crack Repair
- Tower-Deck Junction Repair
What we did on the Bosphorus Bridge

Bosphorus Bridge Tower Strengthening and Damper Installation
Nunteknik erected 412 tonnes of stiffeners and diaphragms inside the four tower legs of the 15 July Martyrs Bridge (Bosphorus Bridge) in Istanbul, from +4.50 m up to +149.25 m, and installed four viscous dampers between the towers and the deck.
View project →
Bosphorus Bridge Expansion Joint Replacement
Working under live traffic, Nunteknik removed and replaced the expansion joints at the Ortaköy and Beylerbeyi ends of the 15 July Martyrs Bridge (Bosphorus Bridge) in four phases and installed around 215 tonnes of strengthening steel in the deck and viaducts.
View project →
Bosphorus Bridge Orthotropic Deck Crack Repair
Nunteknik repaired 59 fatigue cracks of eight types in the orthotropic steel deck of the 15 July Martyrs Bridge (Bosphorus Bridge) in Istanbul, finishing 33 days after contract signature against a 60-day contract period.
View project →
Bosphorus Bridge Tower-Deck Junction Repair
Nunteknik removed the plates and girders of the widened walkway sections around the towers at the four tower-deck junctions of the 15 July Martyrs Bridge (Bosphorus Bridge) in Istanbul and erected new steel fabricated to the measured dimensions of the old.
View project →From our work on the bridge