1915 Çanakkale Bridge
Opened in 2022, the 1915 Çanakkale Bridge has the longest suspension span in the world at 2,023 m. From the tower tops to the anchor blocks, we worked at many points of the bridge during construction and completion.
The work in brief
Nunteknik worked on five separate packages on the 1915 Çanakkale Bridge between 2019 and 2023, from the towers standing in the sea to the anchor blocks on both sides of the strait.
In 2019 a crew of around 20 made the bolted connections of the temporary working platform while it was assembled at a shipyard in Istanbul. The assembly itself was the shipyard's work. In 2022 we installed the four modular expansion joints between the suspension deck and the approach viaducts, each weighing 55 tonnes and measuring 16.19 m. Their manufacturer delivered them complete. We delivered around 112 tonnes of galvanised steel access structures for the anchor blocks, viaduct piers and side-span piers, from shop drawings to erection. On the two 318 m towers we erected the four artillery shell figures on the leg tops, in pieces of up to 13.5 tonnes. From the towers and the anchor blocks we dismantled around 1,400 tonnes of temporary steelwork that had been put up to build the bridge.
The taking-over certificate for the temporary works removal was issued on 30 January 2023, and the provisional acceptance certificate for the access structures on 3 June 2023.
Where on the bridge we worked
Each number marks one job. Point at a number or a row to see every place it was done.
Swipe sideways → · Lengths to scale, heights exaggerated 2.5×; schematic, not for taking dimensions. Sources: Wikipedia; World Highways; Boskalis; ISSMGE.
- Temporary Working Platform Assembly Support
- Expansion Joint Installation
- Anchor Block and Pier Access Structures
- Tower and Anchorage Temporary Works Removal
- Tower Top Enclosure Erection
What we did on the 1915 Çanakkale Bridge
1915 Çanakkale Bridge Temporary Working Platform Assembly Support
In 2019 Nunteknik supported the assembly, at a shipyard in Istanbul, of the temporary working platform (TWP) that would link the two towers of the 1915 Çanakkale Bridge, providing bolted-connection labour with a crew of around 20.
View project →
1915 Çanakkale Bridge Expansion Joint Installation
On the 1915 Çanakkale Bridge, Nunteknik installed the four 55-tonne modular expansion joints between the suspension deck and the approach viaducts, setting, welding and bolting each 16.19 m unit on site.
View project →
1915 Çanakkale Bridge Anchor Block and Pier Access Structures
Nunteknik delivered, as one package from shop drawings to erection, around 112 tonnes of galvanised steel access structures for the anchor blocks, viaduct piers and side-span piers of the 1915 Çanakkale Bridge.
View project →
1915 Çanakkale Bridge Tower and Anchorage Temporary Works Removal
Nunteknik dismantled around 1,400 tonnes of temporary steelwork from the two towers and two anchor blocks of the 1915 Çanakkale Bridge, working as a subcontractor to the main contractor.
View project →
1915 Çanakkale Bridge Tower Top Enclosure Erection
Nunteknik erected the four steel artillery shell figures on top of the legs of the 1915 Çanakkale Bridge's two 318 m towers, joining pieces of up to 13.5 tonnes with site welds and bolts.
View project →From our work on the bridge