
Fatih Sultan Mehmet Bridge Maintenance Gantry Replacement
Nunteknik removed the travelling maintenance gantry under the main span of the Fatih Sultan Mehmet Bridge and is managing fabrication of its replacement, a four-motor gantry with a 39.86 m clear span.
Replacing the gantry under the main span
The client asked for the travelling maintenance gantry under the main span to be replaced. Our scope of works covers removal of the old gantry, fabrication of the new one, factory testing, transport to and erection on the bridge, electrical and automation works, site testing, commissioning and training. Subcontractors working under our responsibility carry part of the work, including the structural calculations and the steel fabrication.
A gantry that must travel on a 3.6% gradient
The new gantry has a clear span of 39.86 m and is 2.50 m wide, centre to centre. It will travel on rails on eight wheels, with four independent drive motors. The specification requires it to operate in all directions on gradients up to 3.6%, in winds of 45 mph (about 20 m/s), on wet or dry surfaces. Removal and erection both take place under the main span, above the Bosphorus.
Method statement and test track before the bridge
We issued the preliminary method statement in April 2026. We also wrote the inspection and test plan for the steel, mechanical and electrical-automation work, with hold points, and set a rule for the removal: no cutting or welding on the bridge's primary structure and no uncontrolled heat input. Our own crews removed the old gantry. Before it goes onto the bridge, the new gantry will run on a test track set to a 3.6% gradient: synchronised running of the four motors, skew control, braking and emergency stops.
Removal recorded complete, steel at the shop
Interim payment certificate No. 1, dated August 2026, records removal of the old gantry as complete. We issued the mechanical, electrical and automation design package in July 2026. By early October 2026 about 40 tonnes of steel had been delivered to the fabrication shop, the shop drawings were complete, and survey and breaking out of old concrete on the test site were done.
What this project actually required
Not a generic service list — the specific capabilities exercised on this package.
The stages we delivered on this project
Select a stage to see how it was carried out and controlled.
Fabrication
Steel fabricated under our quality control, to approved welding procedures (WPS).
More from the bridge & infrastructure record
Planning comparable bridge or infrastructure work?
Send us the drawings, the scope and the site constraints. We will set out how we would deliver the steelwork, from shop drawings to erection.


