
Fatih Sultan Mehmet Bridge Gusset Plate Fabrication and Site Welding
On the Fatih Sultan Mehmet Bridge in Istanbul, Nunteknik managed the fabrication of additional gusset plates for the hanger replacement and welded them on site to the existing hanger plates with full-penetration welds, using a method developed over two mock-ups.
Additional gusset plates for the hanger replacement
The hangers of the Fatih Sultan Mehmet Bridge were being replaced, and additional gusset plates were to be added at the hanger connections. Detailed design stayed with the main contractor. As a subcontractor, we prepared the shop drawings, the method statement, the quality plan, and the inspection and test plan. We procured the steel and managed fabrication in a partner shop; shop and site painting were also in our scope. Our own crews then fitted and welded the plates to the existing hanger plates on the bridge.
Thick-section welds on existing hanger plates, in situ
The gusset plates had to be welded in situ to the existing hanger plates along the south and north walkways. In thick-section full-penetration welding, distortion had to be kept under control. Site welding could not start until the method statement, weld map, programme, risk assessment, quality plan, inspection and test plan and welder certificates were complete.
Mock-ups first, then site welding
The welding method was trialled on two mock-ups before site work. The first failed its magnetic particle test, and we revised the method. On the second, we also had an accredited laboratory run macro and hardness tests. On site, we clamped each plate with wedges and a fit-up jig we designed to the socket dimensions, tack-welded it and braced it with a strongback. We welded under a tent with preheat, starting with a root pass on ceramic backing and alternating between the two sides. An inspection firm carried out NDT 24 hours later.
Traceability register and inspection records
The August 2022 site report records fit-up and welding as complete on the south and north walkways. A traceability register holds the heat number, welder and inspection report numbers for the plates. The project file contains fit-up, dimensional, visual, ultrasonic and magnetic particle records, and paint inspection reports dated October 2022.
What this project actually required
Not a generic service list — the specific capabilities exercised on this package.
The stages we delivered on this project
Select a stage to see how it was carried out and controlled.
Engineering
Engineering and method statements, approved before work starts.
Fabrication
Steel fabricated in EN 1090 certified partner shops under our quality control, to approved welding procedures (WPS).
Erection
Steel erected by our own crews and, where the work calls for it, by subcontractors we manage.
Testing
Non-destructive testing of critical welds.
From the fabrication shop to the completed structure
More from the bridge & infrastructure record
Planning comparable bridge or infrastructure work?
Send us the drawings, the scope and the site constraints. We will set out how we would deliver the steelwork, from shop drawings to erection.





