"One contract" is the shortest description of how we work. The client signs with us, and the steel frame, the concrete it stands on and the envelope around it are ours to deliver. The industry calls this single-point responsibility.
It is easy to read more into that term than it means, so the boundary comes first. This is not design-build. On most of our projects the client's engineers design the building, and we build it from their drawings.
Where a steel-heavy build goes wrong
On a steel-heavy building, the risk sits less inside each trade than between them: where the steel lands on the concrete, where services cross the frame, where the envelope closes the structure.
We took over a 19,814 m² social facility and trade centre in İkitelli, Istanbul, at shell stage. The first phase had been built under a separate contract. A joint survey with the client's inspection unit found three issues. The roof steelwork needed strengthening. The perimeter retaining wall clashed with utility networks. The wet areas did not match the structural design.
None of these was a defect inside one trade. Each sat at a junction between two scopes, and each surfaced only when the next contractor arrived.
That is the problem one contract is meant to solve. When the junction is inside one contract, the clash is found before the second trade starts, and there is no argument about whose it is.
What the contract covers
On a steel-heavy building our contract normally covers:
the steel frame: shop drawings, steel procurement, fabrication management, erection and connections;
the civil works the frame depends on: excavation, foundations, the concrete basement and composite floors;
the envelope: roof and façade;
where the contract includes them, building services, finishes and landscaping.
We erect the steel with our own crews, and on some jobs with subcontractors we manage. Civil, MEP and finishing trades are subcontractors we manage, inspected against our own ITP and inspection forms.
On a health sciences faculty and clinic in Eyüp, Istanbul, we broke the works into 47 packages, from demolition and strip-out through structural steelwork and façade to raised floors and lead shielding. Each package went to an approved specialist subcontractor under our coordination. Shop drawings, subcontractor coordination, and the testing and commissioning of electrical and mechanical systems stayed with us.
What it does not cover
The design. In most of our work the client's engineers design the building, and we take it from their drawings.
Process equipment and the production line. We do not supply, design or commission them. Where the client asks, we install them on a labour basis under the manufacturer's supervision, as we did for the line machinery at a metals plant in Çorlu.
Fabrication in our own shop. Fabrication runs in EN 1090 certified partner shops, under our responsibility.
Within those limits, the scope changes from job to job. On the business center described below, fit-out and MEP were outside our contract. On the trade centre above, they were inside it. The contract decides, and the scope list should say so line by line.
One contract is not one invoice
A contractor can hold every subcontract and still leave the client to manage the interfaces. Three questions show the difference:
Who produces the shop drawings for each trade, and who checks them against each other before anything is fabricated?
When the scope grows during the works, does it go into the same contract or into a new one with a new party?
Whose ITP do the subcontracted trades work to, and who signs their inspection records?
If the answer to any of them is "the client", the client is still managing the interfaces.
One project: a business center in İkitelli
We built the structure and envelope of an 8,093 m² business center in İkitelli, Istanbul, as main contractor under a single contract. Our scope covered excavation, bored-pile shoring, the reinforced-concrete basement and foundations, the steel frame and the composite floors. We were also the licensed building contractor.
The steel frame sat on a basement we had built ourselves. We supplied the shop drawings and the material, fabrication ran in a partner shop under our responsibility, and on site we erected 1,160 assemblies, around 412 tonnes of steel, with bolted connections. The floors were finished with metal decking, shear studs and concrete on the same programme.
While the work was under way, the scope grew by four packages: foundation-level services, roof parapets and gutters, internal walls with steel lintels, and the façade, for which we also produced the shop drawings and the technical specification. All four went into the same contract.
The acceptance board inspected the works on site on 31 July 2025. The acceptance certificate records that the works conform to the contract and its annexes, with no omissions or defects preventing acceptance.
Send us the drawings and the programme. We will set out what one contract would cover on your project, and what it would not.