Bridge Expansion Joint Replacement Under Live Traffic

In short
Replacing an expansion joint on a bridge open to traffic is more than swapping the joint. The method depends on which lanes can be closed, which parts of the deck must be removed, the lifting conditions and the temperature at installation. We develop the method around these constraints, plan the lifts and hand over the installation with its records.

A modular expansion joint arrives from its manufacturer as a finished product. At first sight the job looks simple: lift the old joint out and lower the new one in with a crane. But what if the bridge has to stay open to traffic while you do it?

Then knowing how to lift the joint is not enough. Your working area is limited to the lanes you are allowed to close. On some jobs the joint beams, the deck plate and the ribs have to be replaced along with the old joint. Positioning and welding the new joint and tightening its bolts must follow a specified sequence.

We have replaced expansion joints under these conditions on the 15 July Martyrs Bridge (Bosphorus Bridge) and on the 1915 Çanakkale Bridge. On both bridges the joints came complete from their manufacturer. Our responsibility was to plan how they would be installed and to carry it out on site.

The joint is only part of the job

At both ends of the Bosphorus Bridge, the old expansion joints gave way to new modular joints. The work did not stop at the joints. At the joint zones the box girder end diaphragms, the deck plates and the longitudinal ribs were replaced too, and around 215 tonnes of strengthening steel went into the deck and viaducts.

On the 1915 Çanakkale Bridge the scope was different. The four modular joints came complete from their manufacturer. Our work started with loading at the laydown area, ran through transport, lifting, positioning and connection, and finished with corrosion protection of the weld areas.

So the same job title covered two different scopes. On one bridge the steel around the joint was replaced along with it. On the other, finished joints were installed into the existing bridge.

That is why, when you assess a joint replacement, the first thing to look at is not the joint itself but which parts of the joint zone will be replaced.

On both bridges the manufacturer supplied the joints and we installed them. Depending on the scope, we can take on supply and installation together. On the Fatih Sultan Mehmet Bridge, we have carried out maintenance on the expansion joints.

The lane closures set the phasing

The Bosphorus Bridge carries six lanes of traffic, and each phase of the work closed only two of them. The joint replacement was done in four phases. The programme allowed 80 days; we finished in 75.

The width of the working area was one of the main constraints on the method. Each time, the joint, the deck panel and the diaphragm had to be replaced inside a two-lane strip, with traffic still running in the other lanes.

The main contractor organised the lane closures and the traffic management, and we worked inside those closures.

Every phase followed the same order. First we removed the existing joint welds using air carbon arc gouging. Then we lifted the old joint and its beams out with a mobile crane and plasma-cut the deck plate and ribs. We placed, bolted and welded the new deck section, and installed the expansion joint after that.

The four phases were more than a division in the programme. In each one, removal, lifting, erection of the new steel and setting of the joint all took place in the same narrow working area.

The joint is set to the temperature on the day

On the 1915 Çanakkale Bridge, each of the four modular joints weighed 55 tonnes and measured 16.19 m.

The joint's end plate had to sit on the steel deck 1,485 mm from a diaphragm, and the joint opening had to be set to the temperature at the time of installation.

That is two separate checks: where the joint sits on the bridge, and how wide its opening is for the temperature.

Lowering the joint into the right position is not enough on its own. Its opening has to be preset for the conditions on the day as well.

A 350-tonne mobile crane was provided to us. We prepared the lift plan and lowered the joints into place, then positioned each one with hydraulic jacks and preset its opening to the temperature on the day.

A third-party survey firm took the position and level measurements for us.

In this work the lift plan, the positioning and the temperature setting cannot be treated separately. The crane brings the joint to its place; we use the jacks to adjust its position and opening and check the settings by measurement.

The bridge designer determines the welding sequence

On Çanakkale, most of our welds were in 35–50 mm S460M plate.

The point was not only to make the connections. The welding was also required to transfer no residual stress into the bridge sections.

So we did not choose the weld sequence ourselves. We followed the sequence set out in the bridge designer's response to a technical query: it started at the end plate and finished with bolt tightening.

The working space was another constraint. The stiffener welds lay beneath the cover plate in a confined space. We accessed this space through manholes and a 150 mm access opening.

We ventilated the space with fans and welded to our own welding procedure specifications (WPSs), in processes 136 and 136+121.

On the Bosphorus Bridge, welding was governed by AASHTO/AWS D1.5, the bridge welding code.

That job also involved an engineering decision of its own. The design called for American W sections. We proposed equivalent European sections instead, showed the equivalence by comparing load capacities, and our comparison was approved.

On both bridges, the welding and connection details had to meet the bridge design requirements and be feasible to carry out on site.

Finishing the installation is not the same as handing it over

On Çanakkale, once the four joints were installed, we prepared a separate set of records for each one.

These included fit-up reports, weld logs, non-destructive testing (NDT) reports and bolt-tightening reports, plus two paint inspection reports covering all four joints.

We carried out inspections and checks at the points specified in the inspection and test plan (ITP) we had prepared. NDT was carried out by third-party inspection firms we engaged. The inspection requests for all four joints were closed.

On the Bosphorus Bridge, we handed the work over with as-built drawings.

After the client and Nunteknik inspected the work together on site, the final acceptance record was signed in May 2018. It stated that there were no grounds preventing acceptance.

These records are not there just to complete the file. They show which checks the work has been through.

A joint seated in place with its welds finished means the installation is complete. Handing it over also needs the connections, the measurements and the relevant inspections on record.

Who does what?

A joint replacement involves several parties. Before work starts, the scopes of the joint manufacturer, the bridge designer, the main contractor and the installation team need to be separated.

We developed the method statements for both the Bosphorus and Çanakkale bridges. On Çanakkale we also prepared the lift plan and the ITP.

Depending on our scope, we prepare the shop, erection and as-built drawings. We design the temporary access systems and the lifting equipment on all our jobs, within our own engineering scope.

Where we take design-and-build responsibility, our own engineers can also design the deck details at the joint zone and the strengthening steel. The maintenance gantry for the Fatih Sultan Mehmet Bridge is one example: we designed it, and a subcontractor carried out the structural calculations.

We carry out installation with our own crews and, where needed, with subcontractors we manage. Strengthening steel under our responsibility is fabricated in EN 1090 certified partner shops. Survey and NDT are carried out by specialist third-party firms we engage.

There is also work we do not take on.

We do not design or manufacture the modular expansion joint itself. That is the joint manufacturer's field.

On the Bosphorus and Çanakkale bridges, the bridge designer was responsible for designing the permanent structure and determining the welding sequence. We carried out the work to that design and those technical instructions.

On those jobs, traffic management and lane closures were within the main contractor's scope as well.

The distinction matters. Taking on the joint installation on a bridge does not mean taking on the design of its permanent structure or its traffic management.

Where to start when you plan a joint replacement

When I assess the scope of a job like this, I look at three things first:

  1. Which steel members will be replaced along with the joint? Is it only a finished joint to install, or are the deck plate, ribs and diaphragms part of the work?

  2. How much space is available for the work? Can the bridge be closed completely, or is the work limited to certain lanes?

  3. What are the installation and acceptance conditions? How are the temperature-based setting of the joint, the weld sequence and the survey and inspection requirements defined?

When the answer to any of these changes, the method may change with it.

Send us the joint drawings and the deck details at the joint zone, and tell us which lanes can be closed. Let us know whether the bridge will stay open to traffic throughout the work.

From there we can work through the removal and installation phases, the lifting method and the welding together. We will also agree, before work starts, whether supply of the joint and design responsibility are in the scope.

Share this note
Written by
Muhammed Kahya on site at the 1915 Çanakkale Bridge

Muhammed Kahya

Civil Engineer · Deputy General Manager16 years in the field

Deputy General Manager at Nunteknik. Runs the company's operations on bridge, industrial and commercial steel contracts.

Member, Chamber of Civil Engineers of Türkiye (İMO)Occupational health and safety specialist, Class C
Profile and other notes →
Technical question

Didn’t this note answer your question?

Technical enquiries reach the engineering team directly. Send your drawings or describe the constraint — we answer with the same detail we write in.