
Marmara Ereğlisi LNG Terminal: Jetty and Plant Structural Steelwork
GMK fabricated and erected about 2,000 tonnes of steel for the jetty, berthing platforms, pipe bridge and plant roofs of the Marmara Ereğlisi LNG Terminal in Tekirdağ, Türkiye, in 1992–1994, fitting each 40-tonne platform to its pile section onshore.
Jetty and plant steelwork for an LNG terminal
The main contractor for the Marmara Ereğlisi LNG Terminal awarded GMK the steelwork for the jetty, where liquefied natural gas is unloaded from ships, and for the onshore plant. The scope of works covered pile driving, the berthing platforms at sea and the walkways between them, the steel supports of the pipe bridge and the steel roofs of the plant buildings. GMK prepared the shop drawings and the erection method statement. Process piping was outside its scope.
Connections below the waterline, at sea
The berthing platforms were connected to their piles at elevation −2.50 m, below the water surface. The piles are steel, 2,200 mm in diameter, and each platform weighs 40 tonnes. The walkways linking the platforms are 50 m long each and had to reach the jetty over water before they could be lifted into place. Wave and weather conditions governed every step taken at sea.
Platforms fitted onshore, set in place at sea
GMK cut the driven piles at elevation −2.50 m and took the upper sections ashore. It fabricated the berthing platforms on land and fitted them to these pile sections, which moved the platform-to-pile connection out of the water. Each pile-and-platform unit then went back into the sea and was rejoined to the lower pile at the cut elevation, below the waterline. Once all platforms were in place, GMK shipped the onshore-fabricated walkways out by barge and lifted them by crane into position between the platforms.
About 2,000 tonnes of steel, from jetty to roofs
GMK fabricated and erected about 2,000 tonnes of steel in total, across the jetty, berthing platforms, walkways, pipe bridge and roofs. Joined by the walkways, the platforms form the jetty where LNG carriers berth and the gas is pumped ashore. The terminal was commissioned in 1994.
What this project actually required
Not a generic service list — the specific capabilities exercised on this package.
Stages delivered on this project
From site works to the completed structure
More from the industrial facilities record
Planning a comparable industrial facility?
One contract. Steel to finish. Tell us the scope and we'll come back to you under single-point responsibility.









